Electrical Contracting/Agriculture
Despite external delays, PDC crews made their deadlines and started up the mill with no complications.

10,000 sq. ft.
warehouse construction
58
tanks wired
18,250 feet
conduit installed
69
motors installed
PDC Electrical Contractors assisted in design and and handled the electrical installation for a new Honey Creek Feed Mill. After groundbreaking, construction was slowed by heavy rains over two months. A delay in concrete work pushing steel erection into winter, thereby delaying interior electrical work. The contractor for the steel building was replaced, causing further delays. PDC used extra work hours to get 69 motors installed, 58 tanks wired, and 18,250 feet of conduit installed. The amount of work that had to be done in the cold and at high elevations made the job challenging, but PDC crews pushed through, made their deadlines and started up the mill with no complications.
PDC received the ABC WI 2017 Projects of Distinction Gold Award.
People Power Performance
Ready to experience expert solutions with a caring touch? Contact us to learn more about our comprehensive electrical, automation, motor, and distribution services. Whether you have questions or want to start a partnership, our team is here for you. All fields marked with an asterisk (*) are required fields.
PDC Corporate Headquarters
1065 5th Avenue PO Box 537 Monroe, WI 53566
Hours
Monday–Friday: 7:00 AM–4:30 PM
All fields marked with an asterisk (*) are required fields.